Milestones / Timeline of Mavin (1984 - 1989)
1984 - 1989
- Turnover of less than 1 Crore
- Small contracts of maintenance, R & M of substations including trading
1984
- Electrical contractor for small projects
1985
- Mavin launched in the field of Power sector by taking Maintenance Contract for renovation and Modernization of EHV Substations
1986
- Started Trading Procurement Services for Maharashtra State Electricity Board
1987
- Company received Electrical Contractor License and subsequently first Contract for Lines was executed at Kandhar in Nanded Dist. Carried out Maintenance of 50 Substations under Annual Maintenance Contract
1988
- Received first Contract for 33/11KV Substation at Aurala in Aurangabad Dist. and Completed well before schedule time
1989
- Completed 100 Substations in AMC, set up manufacturing unit for HT and Switchgears Protection device for Substation
- Received orders of 5 Nos. of Sub stations and Executed in Aurangabad, Beed and Osmanabad Dist